PAO NK Rosneft |
Authority Engineering and Detail Engineering development for PAO NK Rosneft Operational Product Metering System Project (technical client: OOO RN-Nakhodkanefteprodukt) |
PAO NK Rosneft |
|
|
Calculation of maximum discharge of gaseous hydrocarbons from process units to offsite flare header and a flowrate of gas to flare utilization. PO documentation development for a closed-type flare. |
OAO Slavneft-YANOS |
|
Updating of Construction Method Statement section for AO RNPK Gas Compression Unit & Offsite Flare System Revamping Project |
AO RNPK |
|
Detail Engineering documentation development for Visbreaker revamping
|
AO RNPK |
|
Detail Engineering development for AO ANKK Diesel Hydrotreating Unit Project |
AO Angarskneftekhimproyekt |
PAO Gazprom |
Detail Engineering development for Integrated Ethane-Ethylene Plant Project at Novourengoiskii Gas Chemical Complex |
Linde |
|
|
Supervision for Integrated Ethane-Ethylene Plant Project at Novourengoiskii Gas Chemical Complex |
Linde |
|
Follow-on of the construction of Novourengoiskii Gas Chemical Complex Project |
OOO NGCC |
|
Preparation of close-out cost-estimate documentation for the Novourengoiskii Gas Chemical Complex Project |
OOO PF VIS |
|
Development and technical & economic analysis of technology for matrix oil integrated processing involving maximum recovery of valuable products |
PAO Gazprom |
|
Revamping of condensate stabilization unit at Sosnogorsk Gas Processing Plant |
OOO Gazprom pererabotka |
|
Revamping of wastewater treatment facilities |
OOO Gazprom pererabotka |
|
Revamping of off-site utilities systems at Sosnogorsk Gas Processing Plant |
OOO Gazprom pererabotka |
|
Revamping of finished product tank farms and loading systems at Sosnogorsk Gas Processing Plant
|
OOO Gazprom pererabotka |
PAO Gazprom neft |
Authority Engineering and Detail Engineering development for Catalyst Plant Project at Gazprom neft - Omsk Refinery
|
PAO Gazprom neft |
|
|
Civil & Structural Detail Engineering development for CORU at AO Gazprom neft - Moscow Refinery |
Tecnimont Russia |
|
Development of Feasibility Study for the modernization of MEA treatment unit at Diesel Hydrotreater
|
AO Gazprom neft - Moscow Refinery |
|
Engineering and consultancy services to AO Gazprom neft - Moscow Refinery |
AO Gazprom neft - Moscow Refinery |
|
Development of general arrangement drawings and details for vacuum column 100 Т-105 for AO Gazprom neft - Moscow Refinery |
VOKENERGOMASH IPTs |
|
Detail Engineering development for replacement of Hydrotreater pumps |
AO Gazprom neft - Moscow Refinery |
|
Approval of operating procedures at Gazprom neft - Omsk Refinery |
AO Gazprom neft - Omsk Refinery |
|
Detail Engineering development for Catalyst Plant Efficiency Improvement Project at Gazprom neft - Omsk Refinery |
AO Gazprom neft - Omsk Refinery |
|
Supervision for Catalyst Plant Efficiency Improvement Project at Gazprom neft - Omsk Refinery |
AO Gazprom neft - Omsk Refinery |
PAO Tatneft |
Detail Engineering and technical follow-on of equipment procurement for off-site facilities, Phase 1.4, AO TANECO |
PAO Tatneft |
|
|
Supervision during the construction of AO TANECO facilities |
PAO Tatneft |
|
Supervision for AO TANECO heavy coker gas oil hydrotreater project |
PAO Tatneft |
|
Detail Engineering development for AO TANECO Heat & Hot Water Unit |
PAO Tatneft |
|
Detail Engineering development for domestic wastewater treatment facility with reference to AO TANECO networks |
PAO Tatneft |
|
Authority Engineering and Detail Engineering development, technical follow-on of equipment procurement for off-site facilities, AO TANECO CDU/VDU
|
PAO Tatneft |
|
Detail Engineering development for a system of conditionally-contaminated LP steam condensate heat recovery for the water demineralization and condensate treatment system with reference to AO TANECO networks |
PAO Tatneft |
|
Supervision for AO TANECO project of the construction of integrated hydrocracker and off-site facilities - Start-up Complex 1b, Phase I
|
PAO Tatneft |
|
Supervision for Ashalchinskoye Field Development and infrastructure facilities, designed for production of 800 kTA of super viscous oil
|
PAO Tatneft |
|
Detail Engineering development for the replacement of gas analyzers of Hydrogen Plant heater for PAO Tatneft |
AO TANECO
|
|
Authority Engineering and Detail Engineering development, technical follow-on of equipment procurement for PAO Tatneft Hydroconversion Unit |
OOO INKO-TEK |
|
Technical follow-on of process equipment manufacturing for PAO Tatneft Hydroconversion Unit
|
OOO INKO-TEK |
|
Detail Engineering development and Engineering Services for AO TANECO Heavy Coker Gas Oil Hydrotreater Project |
OOO INKO-TEK |
|
Authority Engineering development for Bolshe-Kamenskoye Upheaval Project
|
PAO Tatneft |
|
Detail Engineering development for Bolshe-Kamenskoye Upheaval Project at Ashalchinskoye Field
|
PAO Tatneft |
|
Authority Engineering for Yuzhno-Ashalchinskoye Upheaval Development Project
|
PAO Tatneft |
|
Detail Engineering development for the Severo-Ashalchinskaya Boiler House at Severo-Ashalchinskoye Upheaval Project
|
PAO Tatneft |
|
Detail Engineering documentation development for Yuzhno-Ashalchinskoye Upheaval Development Project
|
PAO Tatneft |
Total |
Updating and follow-on of design & cost estimate documentation for Kharyaga Field Development Project |
AO Giprovostokneft |
|
OOO SIBUR |
Consulting services for OOO ZapSibNefteKhim Petrochemical Complex Project |
OOO ZapSibNefteKhim |
|
|
Verification of completeness and quality control of construction supervision for OOO ZapSibNefteKhim Petrochemical Complex Project |
OOO ZapSibNefteKhim |
|
Preparation of Authority Engineering documentation for OOO ZapSibNefteKhim Petrochemical Complex Project |
OOO ZapSibNefteKhim |
|
Updating of geotechnical survey reports for OOO ZapSibNefteKhim Petrochemical Complex |
OOO ZapSibNefteKhim |
|
Updating of general and special sections of Authority Engineering documentation for OOO ZapSibNefteKhim Petrochemical Complex |
OOO ZapSibNefteKhim |
|
Updating of Authority Engineering for Ethylene Plant at OOO ZapSibNefteKhim Petrochemical Complex |
OOO ZapSibNefteKhim |
|
Civil & Structural Steel Detail Engineering documentation for OOO ZapSibNefteKhim Petrochemical Complex Project |
Linde |
|
Detail Engineering development for technical reequipment of the isobutane dehydrogenation unit (BK-2) involving its expansion to at least 200 kTA on 100% isobutylene for OOO SIBUR Tobolsk
|
OOO SIBUR Tobolsk |
AO MKhK Euro-Chem |
Detail Engineering documentation development for Kingisepp Ammonia Plant Project - Water Unit
|
ZAO Ionnoobmenniie tekhnologii |
|
AO NK KMG |
Pavlodar Oil Chemistry Refinery Upgrading Project - Authority Engineering |
ROMINSERF |
|
|
Technical assistance in preparation of summary specification sheets and acquisition of technical & commercial proposals from potential vendors for POCR SC 2 & 3 |
ROMINSERF |
|
Translation of Authority Engineering documentation |
ROMINSERF |
|
Adaptation of the existing units of Start-up Complexes 2 & 3 to Standards of the Republic of Kazakhstan in the course of POCR upgrading |
ROMINSERF |
Kazakhstan Petrochemical Industries Inc. |
Pre-project and design activities for updating of the process design section for Feasibility Study and Authority Engineering documentation for Integrated Gas Chemical Complex Project in Atyrau region
|
Ekspert Sertifikatsiia |
|
|
Updating of the process design section for Feasibility Study and Authority Engineering documentation for Integrated Gas Chemical Complex Project in Atyrau region
|
Kazakhstan Petrochemical Industries Inc. |
OAO TAIF |
Engineering consultancy services for PAO Nizhnekamskneftekhim Project of a 600-kTA ethylene plant including off-site facilities
|
Toyo Engineering Corporation |
|
AO Salavatskii NKhZ |
Authority Engineering development for Small-Capacity Naphthyl Plant Project at AO Salavatskii NKhZ
|
GUP Bashgiproneftekhim |
|
|
Mechanical design of High-Pressure Equipment for Small-Capacity Naphthyl Plant Project at AO Salavatskii NKhZ
|
GUP Bashgiproneftekhim |
OOO VPK-Oil |
Follow-up of Basic Design Acceptance - Diesel Hydrotreating Unit at Kochenevskii Refinery |
OOO VPK-Oil |
|
|
Development of Authority Engineering and Detail Engineering for a 300-kTA diesel hydrotreating unit at Kochenevskii Refinery
|
OOO VPK-Oil |
PAO Novolipetskii Metallurgicheskii Kombinat (PAO NLMK) |
Pre-project development: PAO NLMK. Marketing Study "Products of vacuum residue conversion into petroleum coke or petroleum-based additive" |
PAO Novolipetskii Metallurgicheskii Kombinat |
|