Oil Refining
OAO TatneftHydrocrackingComplex, 2.9 MTA – 2014 OAO VNIPIneft Scope of Work: Authority Engineering,DetailedDesign, Procurement,      Supervision.
ZAO RNPK VGO      Hydrocracking Complex,2 MTA – 2014OAO VNIPIneft Scope of Work: Authority Engineering
Sulfur Recovery Unit at the MMC Norilsk Nickel      Polar Division Copper Plant - 2014OAOVNIPIneftScopeofWork: AuthorityEngineering
OOO LUKOIL-Volgogradneftepererabotka Integrated      CDU/VDU, 6 MTA - 2014OAOVNIPIneftScopeofWork: Authority Engineering and Detailed Design
OAO Gazprom Neft – Moscow Refinery Isomerization      Unit, 650 kTA – 2013OAOVNIPIneftScopeofWork: Basic Design Acceptance, Detailed Design,Supervision
OAO Gazprom Neft – Moscow Refinery Diesel      Hydrotreating Unit, 320 kTA- 2013OAOVNIPIneftScopeofWork: Authority Engineering and Detailed Design, Supervision
OOO LUKOIL-Volgogradneftepererabotka Atmospheric      – Vacuum Distillation Unit - 2012OAOVNIPIneftScopeofWork: Authority Engineering
OAO Angarskneftekhimproyekt Diesel Hydrotreating Unit-      2012OAOVNIPIneftScopeofWork: Authority Engineering
OAO Gazprom Neft – Moscow RefineryPSA Unit - 2011OAOVNIPIneftScopeofWork:Authority Engineering and Detailed Design, Supervision
OJSC TANECO CDU/VDU, 7 MTA - 2010 OAOVNIPIneftScopeofWork: Basic Design, Authority Engineering and Detailed      Design, Procurement, Supervision
OOO PO KirishinefteorgsintezCapacity: 4.9 MTA (vacuum distillation), 2.2 MTA (visbreaking)
 OAOVNIPIneftScopeofWork: Basic Design Acceptance; Detailed Design, Procurement.
 Commissioningdate: 2009
ZAO RNPK Deep Conversion      ComplexCapacity: 2.5 MTA
 OAOVNIPIneftScopeofWork: BasicDesignAcceptance, AuthorityEngineeringandDetailedDesign(jointlywithCB&ILummus);      Procurement; Supervision.
 Commissioningdate: 2005-2006
OAO TAIF-NK Catalytic Cracking ComplexCapacity: 850 kTA
 OAOVNIPIneftScopeofWork: ActingasaGeneralDesigner; BasicDesign(jointly      with OAO VNIINP);DetailedDesign; Procurement; Supervision.
 Commissioningdate: 2005
OAO      Slavneft-Yaroslavnefteorgsintez Deep Conversion ComplexCapacity: 2.1 MTA
 OAOVNIPIneftScopeofWork: BasicDesignAcceptance, DetailedDesign(jointlywithToyoEngineeringCorporation);      Supervision.
 Commissioningdate: 2005
OOO      LUKOIL-Permnefteorgsintez VGO Hydrocracking ComplexCapacity: 3.5 MTA - Plant
 OAOVNIPIneftScopeofWork: ActingasaGeneralDesigner; Basic Design Acceptance;      DetailedDesign, Procurement, Supervision.
 Commissioning date: 2004
ZAO RNPK Catalytic Cracking Complex  Capacity: 2.5 MTAOAOVNIPIneftScopeofWork: DetailedDesign, Supervision.
 Commissioning date: 2001
 |  |